Despite the sparsely populated area, construction will partly take place on narrow streets right next to housing. Widening of the streets will sometimes take place very close to residential areas, which will require special care.

The natural gas and power lines in the area pose an additional challenge. For example, the project involves some 300 km of pillar stabilisations in order to improve the load bearing capacity of the clay soil. The sewer lines and street structures may only be constructed after this stage. In connection with the street construction, the natural gas lines will be protected with concrete elements, and excavation near the lines will use rock splitting rather than blasting.

The customer in the nearly EUR 11 million contract is the City of Espoo, and the execution schedule is from June 2019 to May 2021.

Kurttilan kadut

Status

Completed

Category

Address

Salakuljettajankatu,
Espoo

Completion

05/2021

Project Leader

Petri Ketonen

Project personnel

Position Name Phone Email
Responsible Site Manager Heikki Mustonen +358 40 084 3572 heikki.mustonen(a)kreate.fi

Articles

Kreate pursues growth in Sweden: new CEO appointed

Kenneth Wahlqvist has been appointed CEO of Kreate Sverige as of 1.4.2025. He has worked over 30 years at Skanska, leading large-scale construction projects and the infrastructure construction business unit,…

Kreate has signed an agreement for the development stage of the alliance contract for the Kirjalansalmi and Hessundinsalmi bridges, one of the most demanding bridge projects in Finland

The Finnish Transport Infrastructure Agency and Kreate have signed the development stage alliance agreement for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project, which will be one of the…