In an extensive contract, we moved the main thoroughfare of Hervanta, one of the largest suburbs in Finland, ten metres east. At the same time, we made new municipal engineering in the area, built a stormwater pool and did surfacing work for the Hervanta thoroughfare.

During the contract, our bridge experts built two light traffic bridges over the Hervanta thoroughfare, the Asia Bridge and the Africa Bridge. The more northern of these, the Asia Bridge, is connected to a 60-metre-long, trough-shaped supporting wall, making a bend of more than 90 degrees and thus becoming S-shaped. The speciality of the African Bridge is its deck structure, which widens significantly towards its western end, and the colourful special railings, for which we built unique web-like lighting.

The bridges were built almost simultaneously, and the construction work on the land supports was agreed in cooperation with our transport infrastructure builders. Building the Africa Bridge in a very narrow strip between the apartment buildings east of the Hervanta thoroughfare posed a challenge of its own. Both bridges are slab bridges partly based on bored piles, for which Kreate’s joint venture KFS Finland carried out the piling.

We worked efficiently in accordance with the City of Tampere’s emissions and employment requirements. We take into account the circular economy, for example by utilising quarried material in the structural layers of the road and by using timber and piling pipes left over from our other construction sites.

The customers for the contract were the City of Tampere, Tampereen Vesi Oy and Tampereen Sähkölaitos Oy. The contract time was from May 2022 to October 2023, and the contract price was some 7.5 million euros.

Kreate toteuttaa Hervannan pohjoisakselin rakennusurakan Tampereella

Status

Completed

Category

Address

Insinöörinkatu 11, Tampere

Completion

10/2023

Project Leader

Jarkko Jokinen

Project personnel

Position Name Phone Email
Construction Manager Jarkko Jokinen +358 50 380 3110 jarkko.jokinen(a)kreate.fi
Worksite Manager Alvar Peltola +358 50 410 8466 alvar.peltola(a)kreate.fi
Responsible Site Manager, bridges Mikko Heija +358 45 262 4226 mikko.heija(a)kreate.fi

Articles

Kreate has signed an agreement for the development stage of the alliance contract for the Kirjalansalmi and Hessundinsalmi bridges, one of the most demanding bridge projects in Finland

The Finnish Transport Infrastructure Agency and Kreate have signed the development stage alliance agreement for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project, which will be one of the…

Kreate Group’s joint venture KFS Finland has completed the acquisition of NordPile Oy

KFS Finland Oy, which is equally owned by Kreate Group Plc and the global Keller Group plc, announced on 8 September 2021 that it has signed an agreement concerning the…

The Crown Bridges joint venture has signed the contract: the construction of Kruunuvuorensilta, the longest bridge in Finland, will begin in October

The Crown Bridges joint venture formed by Kreate and YIT has signed a contract with the City of Helsinki regarding the Crown Bridges project. The contract comprises the construction of…