The earthworks of the large-scale project included, among other things, the excavation for the building trench of the new production facility. The new factory building is 200 metres long and 130 metres wide, and there was a total of approximately 100,000 cubic metres to be quarried. The building is to be located south of the current poultry production facility, partly on top of the current car park and partly east of it.

Kreate’s professionals were also responsible for the construction of Atria’s yard areas and parking areas in a total area of approximately four hectares.  We built the storage fields and solar panel fields, and our work also included earthworks for the energy centre and sewage basin that will be located on the site. Kreate was also responsible for constructing the building technology and process technology pipelines outside the new factory building as well as the main water supply, pressure sewer, district heating and high-voltage cables for the energy centre.

The worksite area was very large, and the quarrying and construction next to the operational factory and production routes brought challenges.

The environmental impact of the earthworks phase was taken into account, for example, by processing the aggregates from the excavated rock for use on the worksite instead of transporting them away. We made full use of the compactable cutting masses in the structures of the solar panel fields built on the site. In this way, we reduced the environmental impacts, use of virgin materials and the resulting costs as well as the congestion of road networks.

The customer for the contract was Atria Oyj. Kreate’s portion of the contract was completed in the summer of 2023, and Atria’s new factory will be finished in 2024 at the earliest.

Kreate mukana Atrian historian suurimmassa investointihankkeessa – Nurmon siipikarjatehtaan maanrakennustyöt etenevät käynnissä olevan tuotannon yhteydessä

Status

Completed

Category

Address

Atriantie 1, Seinäjoki

Completion

07/2023

Project Leader

Ari Välimaa

Project personnel

Position Name Phone Email
Construction Manager Ari Välimaa +358 400 792 472 ari.valimaa(a)kreate.fi
Responsible Site Manager Joonas Kauppinen +358 40 197 7556 joonas.kauppinen(a)kreate.fi

Articles

Kreate has signed an agreement for the development stage of the alliance contract for the Kirjalansalmi and Hessundinsalmi bridges, one of the most demanding bridge projects in Finland

The Finnish Transport Infrastructure Agency and Kreate have signed the development stage alliance agreement for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project, which will be one of the…

Kreate Group’s joint venture KFS Finland has completed the acquisition of NordPile Oy

KFS Finland Oy, which is equally owned by Kreate Group Plc and the global Keller Group plc, announced on 8 September 2021 that it has signed an agreement concerning the…

The Crown Bridges joint venture has signed the contract: the construction of Kruunuvuorensilta, the longest bridge in Finland, will begin in October

The Crown Bridges joint venture formed by Kreate and YIT has signed a contract with the City of Helsinki regarding the Crown Bridges project. The contract comprises the construction of…