Kreate built, among other things, the Kausela-Pukkila section into four lanes; improved the Kausela flyover junction; repaired and replaced waterway bridges on River Aurajoki; and did improvement work on Highway 10 between the ring road and Kaarinantie.

The implementation of the second phase of the E18 Turku ring road required solid technical know-how and efficient scheduling. Problem-solving ability was required especially with regard to the ground conditions and busy traffic. For example, the traffic volumes on Highway 10 were up to 30,000 cars per day.

Challenging ground conditions were encountered especially during the construction of the underpasses and the Aurajoki waterway bridges. Deep trenches were made in the clay-heavy soil in the immediate vicinity of busy thoroughfares, which is why Kreate paid special attention to things such as supporting the trenches and groundwater management.

The second phase of the project started in July 2020 with preparatory work, and construction started in July 2020.

The value of the contract was 35 million euros. The customer was the Finnish Transport Infrastructure Agency, which implemented the project in cooperation with the Municipality of Lieto and the City of Kaarina.

E18 Turun kehätie artikkelikuva verkkosivu

Status

Completed

Category

Address

Valtatie 10 ja E18 risteys
20540 Turku

Completion

12/2022

Project Leader

Sami Laakso

Project personnel

Position Name Phone Email
Project Manager Ilkka Kaarakainen 040 524 7319 ilkka.kaarakainen@kreate.fi

Articles

Kreate has signed an agreement for the development stage of the alliance contract for the Kirjalansalmi and Hessundinsalmi bridges, one of the most demanding bridge projects in Finland

The Finnish Transport Infrastructure Agency and Kreate have signed the development stage alliance agreement for the Highway 180 Kirjalansalmi and Hessundinsalmi bridge renovation project, which will be one of the…

Kreate Group’s joint venture KFS Finland has completed the acquisition of NordPile Oy

KFS Finland Oy, which is equally owned by Kreate Group Plc and the global Keller Group plc, announced on 8 September 2021 that it has signed an agreement concerning the…

The Crown Bridges joint venture has signed the contract: the construction of Kruunuvuorensilta, the longest bridge in Finland, will begin in October

The Crown Bridges joint venture formed by Kreate and YIT has signed a contract with the City of Helsinki regarding the Crown Bridges project. The contract comprises the construction of…