We rebuilt the Kiitola Bridge in Jepua, Uusikaarpelyy, built in the early 1900s. In the project, our bridge contractors first built a working bridge over the Lapua River, then we dismantled the old bridge. Then the foundation work for the new prestressed concrete bridge began.
The supports of the old bridge were retained, and the new bridge was built on piles drilled through the old supports. The drilled piles will be driven by KFS Finland Oy, a joint venture company specialising in specialist foundation engineering at Kreate.
The construction site was located on a river, which posed its own challenges, including the construction of a working bridge, the dismantling of old stone structures and reinforcement work.
The contractor was the City of Uusikaarlepyy, contract period was 6-12/2024.

Status
In progress
Category
Address
Kiitolantie, Jepua
Completion
12/2024
Project manager
Ari Välimaa
Project personnel
Position
Name
Phone
Construction Manager
Ari Välimaa
+358 400 792 472
ari.valimaa@kreate.fii
Worksite Manager
Joonas Kauppinen
+358 40 197 7556
joonas.kauppinen@kreate.fi
Articles

- Newsroom

- Newsroom

- Newsroom
Similar projects


Status
In progress
WE ARE REPLACING THE KOIVISTO AND PIKKUHAARA BRIDGES OVER KOKEMÄENJOKI RIVER ON HIGHWAY 11
12/2025