
LARGE-SCALE STREET AND BRIDGE CONTRACT FOR THE NORTHERN AXIS OF HERVANTA, TAMPERE
Kreate was responsible for the large-scale infrastructure construction contract for the northern axis of Hervanta, where we relocated the area’s most important thoroughfare and built two spectacular light traffic bridges. It was this way that we were able to make versatile use of our strong expertise in thoroughfare, bridge and special foundation construction.
In an extensive contract, we moved the main thoroughfare of Hervanta, one of the largest suburbs in Finland, ten metres east. At the same time, we made new municipal engineering in the area, built a stormwater pool and did surfacing work for the Hervanta thoroughfare.
During the contract, our bridge experts built two light traffic bridges over the Hervanta thoroughfare, the Asia Bridge and the Africa Bridge. The more northern of these, the Asia Bridge, is connected to a 60-metre-long, trough-shaped supporting wall, making a bend of more than 90 degrees and thus becoming S-shaped. The speciality of the African Bridge is its deck structure, which widens significantly towards its western end, and the colourful special railings, for which we built unique web-like lighting.
The bridges were built almost simultaneously, and the construction work on the land supports was agreed in cooperation with our transport infrastructure builders. Building the Africa Bridge in a very narrow strip between the apartment buildings east of the Hervanta thoroughfare posed a challenge of its own. Both bridges are slab bridges partly based on bored piles, for which Kreate’s joint venture KFS Finland carried out the piling.
We worked efficiently in accordance with the City of Tampere’s emissions and employment requirements. We take into account the circular economy, for example by utilising quarried material in the structural layers of the road and by using timber and piling pipes left over from our other construction sites.
The customers for the contract were the City of Tampere, Tampereen Vesi Oy and Tampereen Sähkölaitos Oy. The contract time was from May 2022 to October 2023, and the contract price was some 7.5 million euros.

Status
In progress
Category
Address
Insinöörinkatu 11, Tampere
Completion
10/2023
Project manager
Jarkko Jokinen
Project personnel
Position
Name
Phone
Construction Manager
Jarkko Jokinen
+358 50 380 3110
jarkko.jokinen@kreate.fi
Worksite Manager
Alvar Peltola
+358 50 410 8466
alvar.peltola@kreate.fi
Responsible Site Manager, bridges
Mikko Heija
+358 45 262 4226
mikko.heija@kreate.fi
Similar projects


Status
In progress
WE ARE REPLACING THE KOIVISTO AND PIKKUHAARA BRIDGES OVER KOKEMÄENJOKI RIVER ON HIGHWAY 11
12/2025
