EARTHWORKS AND SITE PREPARATION FOR A RESPONSIBLY IMPLEMENTED REAL ESTATE COMPLEX ON LAURI KORPISEN KATU IN VANTAA
Kreate’s foundation builders were responsible for the earthworks and special foundation construction works for the real estate complex built by Sponda. A 6-floor office building with a parking facility for approximately 650 cars and business premises on the ground floor will be located on Lauri Korpisen katu in Jokiniemi, Vantaa.
The work of Kreate’s professionals included excavation work in an area of almost 15,000 m², such as surface soil removal; excavation of clay soils and contaminated soils; and excavation and shaping of spread foundations. Our specialists in foundation construction were also responsible for the side fillings subsequent to concreting work as well as the drainage and pipe work.
Among other things, the site was made challenging by the train track that runs in the immediate vicinity of the worksite, which had to be taken into account especially during piling. The stabilisation, retaining walls and anchoring were executed together with Kreate’s joint venture, KFS Finland, which specialises in special foundation construction.
The landmark rising in the heart of Tikkurila with its parking garage is the biggest project in the history of Fira, which is the contractor for the project. The project commissioned by Sponda focuses especially on energy efficiency, environmentally responsible solutions and the comfortable use of the facilities. The office property itself produces renewable energy for its own use.
The customer was Sponda Oy. For Kreate’s part, the contract time was from June 2022 to April 2023, and the contract price was approximately 3.4 million euros. The project as a whole will be completed at the turn of 2024–2025.

Status
Completed
Category
Address
Lauri Korpisen katu 9, Vantaa
Completion
04/2023
Project manager
Tatu Tarkiainen
Project personnel
Position
Name
Phone
Construction Manager
Tatu Tarkiainen
+358 50 539 5210
tatu.tarkiainen@kreate.fi
Worksite Manager
Otto Miettinen
+358 50 309 2845
otto.miettinen@kreate.fi
Similar projects

Status
Ongoing
NEW MÄHKÖNSILTA BRIDGE RESTORES MUCH-NEEDED TRANSPORT LINK OVER THE LIEKSA RIVER
12/2026

Status
Ongoing
IMPROVING THE FLOW OF HIGHWAY 8 BY REPLACING THE LAPVÄÄRTINJOKI BRIDGE IN KRISTINESTAD
06/2026