Kreate’s foundations, bridge and railway construction experts worked at Pieksämäki station in a contract where we dismantled the outermost platforms, 1 and 6, over a distance of about 180 metres, after which we rebuilt them raised to meet the accessibility requirements of the European Commission’s PRM-YTE regulation. In addition to installing new platform elements, we replaced the stairs of platform 1 and the canopies and lighting of both platforms, improved guidance and added tactile markings to the passageways. In the contract, we also made individual changes to the track and to safety devices.

For the platform transformation contract, we obtained a synergy benefit from the extensive renovation of the station tunnel at Pieksämäki station that we executed at the same time. In addition to the comprehensive renovation of the tunnel under the train tracks, we also built 75-metre-long covered ramps and above-ground structures at both ends of the tunnel.

The customer for the platform raising contract is the Finnish Transport Infrastructure Agency, and the contract time was from July 2023 to November 2023. The work complemented and continued the change and development works of the City of Pieksämäki in the station area.

Kreate toteuttaa matkustajalaitureiden korotustyöt ja laiturialueen ulkoasun parantaminen osana Pieksämäen asemajärjestelyitä

Status

Completed

Category

Address

Asemakatu 2, Pieksämäki

Completion

11/2023

Project Leader

Mika Seppälä

Project personnel

Position Name Phone Email
Construction Project Manager Mika Seppälä +358 50 316 0707 mika.seppala(a)kreate.fi
Worksite Manager Tomi Pyökeri +358 40 197 8777 tomi.pyokeri(a)kreate.fi