THE NUUTILANMÄKI–JUVA SECTION OF HIGHWAY 5 INCREASED SAFETY AND FLUIDITY ON THE MAIN ROAD IN EASTERN FINLAND
In the massive Nuutilanmäki-Juva project on Highway 5, Kreate built five new flyover junctions, approximately 15 kilometres of a new four-lane highway, a detour and 12 new bridges. Kreate utilised the versatile expertise of its various units, which clearly improved the company’s competitiveness as well.
Highway 5 between Mikkeli and Juva was built as a four-lane road with a median guardrail and junctions at different levels. In the Mikkeli–Nuutilanmäki section, the road was mainly built in a new off-road corridor. In the first phase of the project, a parallel road in the direction of the highway was built, which also served as a detour during work. The parallel road built for the entire duration of the project was located east of the new highway.
The multi-year project included a wide range of different infrastructure construction areas. Kreate’s special expertise and good advance planning guaranteed the efficient implementation and successful completion of the project. Work was carried out throughout the year, and the new highway was opened to traffic in stages in 2020–2021. The entire road was complete in summer 2022. The efficient and safe execution reduced the inconvenience caused to traffic.
The customer was the Finnish Transport Infrastructure Agency, the contract price was more than 41 million euros and the implementation time was from September 2019 to July 2022.

Status
In progress
Category
Address
Tenhusentie 3
Completion
07/2022
Project manager
Timo Tiainen
Project personnel
Position
Name
Phone
Construction Manager
Timo Tiainen
+358 400 152 116
timo.tiainen@kreate.fi
Articles

- Newsroom

- Newsroom

- Newsroom
Similar projects


Status
In progress
WE ARE REPLACING THE KOIVISTO AND PIKKUHAARA BRIDGES OVER KOKEMÄENJOKI RIVER ON HIGHWAY 11
12/2025